Supplier Qualification Matrix - Project Controls

Printer-friendly versionPrinter-friendly versionSend by emailSend by email
Department Project Controls
First Tier Subcontractor/Supplier Must have systems capable of monitoring and controlling costs on a project by project basis. Must demonstrate competence in planning and scheduling work to meet the requirements of the project schedule, and a recognized scheduling program such as Primevera P6 must be used for scheduling larger contracts. Must have effective change control systems.
Second Tier Subcontractor/Supplier Must have systems capable of monitoring and controlling costs on a project by project basis. Must demonstrate competence in planning and scheduling work to meet the requirements of the project schedule, a recognized scheduling program such as Primevera P6 must be used for scheduling larger contracts. Must have effective change control systems.
Third and below Tier Subcontractor/Supplier Same as Second Tier requirements