Overall Hebron Platform Execution Scenario

Main Phases:


  • GBS construction in dry dock - civil and mechanical outfitting (MOF)
  • Tow out and installation at deep water site (DWS)
  • GBS construction at DWS - civil and MOF including solid ballast
  • Assembly of Topsides at nearby pier
  • Float over and deck mating at DWS
  • Hook-up and commissioning Topsides - GBS
  • Tow out and installation at offshore location including grouting
Platform

GBS Construction Sequence